The two best ways of investing energy to produce energy are wind turbines and
nuclear power. However, nuclear is a much better way to provide base-load
electricity. Wind power would have to be converted into hydrogen and back
again to achieve the same result.
Why consider nuclear power in a book about
the transition to renewable energy? In my
view, because nuclear is complementary to
renewables in moving to a sustainable and
largely carbon-free energy future. The reason I
say this is that in most countries, the demand
for electricity has a very large continuous
component - see Figure 1D1. This requires a
reliable supply of electricity which cannot be
readily met from intermittent wind or solar
sources since their electricity cannot be stored
on a large scale.
Nuclear is simply the most appropriate technology
for the job of providing clean baseload
power. (Hydrogen may one day be made
on a large scale from electricity, or directly
from nuclear energy by thermochemical
means and then stored on a large scale for
turning back to electricity, but such developments
are many years away. Even then the
hydrogen will be in higher demand for transport.)
ENERGY BALANCE
The economics of electricity generation are
important. If the costs of building and operating
a power plant cannot profitably be
recouped by selling the electricity, it is not
financially viable. But as energy itself can be
a more fundamental unit of accounting than
money, it is also essential to know which generating
systems produce the best return on the
energy rather than the money invested in
them. Determing this involves Life Cycle
Analysis (LCA).
Analysing the energy balance between inputs
and outputs, however, is complex because the
inputs are diverse, and it is not always clear
how far back they should be taken. For
instance, oil expended to move coal to a power
station, or electricity used to enrich uranium for
nuclear fuel, are generally included in the calculations.
But what about the energy required to
build the train or the enrichment plant? And can
the electricity consumed during enrichment be
compared with the fossil fuel needed for the
train? Many analysts convert kilowatt-hours
(kWh) to kilojoules (kJ), or vice versa, but this
requires them to make assumptions about the
thermal efficiency of the electricity production.
Some inputs are easily quantified, such as the
energy required to produce a tonne of uranium
oxide concentrate at a particular mine, or to
produce a tonne of particular grade of uranium
hexfluoride at a uranium enrichment plant.
Similarly, the energy required to move a tonne
of coal by ship or rail can be identified,
although this will vary considerably depending
on the location of the mine and the power plant.
Moving gas long distances by pipeline is surprisingly
energy-intensive.
Other inputs are less straightforward such as the
energy required to build a 1000 MWe power
plant of a particular kind, or even that to construct
and erect a wind turbine. But all such
energy inputs need to be amortised over the life
of the plant and added to the operational inputs
such as fuel. Also the post-operational energy
requirements for waste management and
decommissioning plants must be included.
There is no such thing as a free kilowatt-hour!
As well as energy costs, the environmental and
health consequences of energy production that
do not appear in the financial accounts need to
be considered as well. Recent studies have
plausibly quantified them in financial terms,
and I will comment on those at the end.
Many energy analysis studies done in the 1970s
seem to have assumed that if nuclear generating
capacity was expanded very rapidly, it would
require so much energy for fuel production and
construction that, for a few years, inputs would
exceed overall outputs. To determine whether
or not this would happen requires the dynamic
analysis of the whole energy system and is not
attempted here. The 1970s studies were also
driven by a perception that primary energy
sources including uranium would become
increasingly difficult and expensive to recover,
and would thus require undue amounts of energy
to access them. This notion has since re-surfaced.
The figures in Figure 1D2 are based as far as
possible on current assumptions and current
data for enrichment, mining and milling, etc.
Where current data are unavailable, that from
earlier studies is used. For nuclear power,
enrichment is clearly the key energy input
where the older diffusion technology is used - it
comprises more than half of all the energy used
in the lifetime of the plant. However, with centrifuge
technology, enrichment takes far less
energy than the construction of the plant itself.
Indeed, the difference between the two processes
is so great that, overall, an input of only a
third of the energy is required to build and operate
a nuclear plant using centrifuge technology
than one fuelled by the older diffusion method.
(Figure 1D2) Life Cycle Energy Requirements for a Nuclear Power Plant |
| GWh (e) | TJ (th) Annual | PJ (th) 30 year |
Inputs | | | |
Mining & Milling (180 t/yr U308 at Ranger) | | 37 | 1.26 |
Conversion (ConverDyn data) | | | 5.63 |
Initial enrichment diffusion @ 2400 kWh/SWU | 576 | | 6.23 |
Urenco centrifuge @ 63 kWh/SWU | 15 | | 0.16 |
Reload enrichment diffusion @ 2400 kWh/SWU | 201 | 2175 | 65.25 |
Urenco centrifuge @ 63 kWh/SWU | 5.3 | 57 | 1.71 |
Fuel Fabrication (ERDA 76/1) | | | 4.32 |
Construction & Operation (ERDA 76/1) | | | 24.69 |
Fuel storage, Waste storage, Transport (ERDA 76/1, Perry
1977), Decommissioning allow | | | 1.0 |
| Total (diffusion enrichment) | 108 |
| Total (centrifuge enrichment) | 39 |
Output: 7 TWh/yr | 7000 | 75.670 | 2 270 PJ |
Input percentage of lifetime output, thermal | (diffusion) | 4.8% |
| (centrifuge) | 1.7% |
Energy ratio (output/input), thermal | (diffusion) | 21 |
| (centrifuge) | 59 |
Assumptions:
Fuel Cycle: 1000 MWe, 30-year life, 80%
capacity factor, enrichment with 0.30% tails
(3.0 SWU/kg for initial 80 t fuel load @ 2.3%
U-235, 4.3 SWU/kg for 3.5% fresh fuel @
19.5 t/yr), 45,000 MWd/t burn-up, 33% thermal
efficiency.
Calculations: Electrical inputs converted to
thermal @ 33% efficiency (x 10 800, kWh to
kJ)
Other figures for front end: Cameco mines
in Saskatchewan input 32 TJ per 180 t U3O8
over 1992-2001 including some capital
works. Urenco enrichment at Capenhurst
input 62.3 kWh/SWU for whole plant in 2001-
02, including infrastructure and capital works.
Other figures for construction (but not
operation) of 1000 MWe PWR power plant
are: 13.6 PJ (Chapman 1975, recalculated),
14.76
PJ (Held 1977, if converted direct), 24.1 PJ
(Perry et al 1977).
Energy payback period. If 30 PJ or 25 PJ is
taken for diffusion and centrifuge enrichment
respectively as the energy capital cost of setting
up, then at 75 PJ/yr output the initial
energy investment is repaid in 5 months or 4
months respectively at full power.
Construction time for nuclear plants is 4-5
years.
The only data available for storage and disposal
of radioactive wastes, notably spent
fuel, suggests that this is a minor contribution
to the energy picture. This is borne out by
personal observation in several countries -
spent fuel sitting quietly in pool storage or
underground is about as passive as you can
imagine. Decommissioning energy requirements
may be considered with wastes, or (as
Vattenfall) with plant construction.
As yet, no energy-input figures seem to have
been published for the fuel cycle that the UK
has been using - the closed cycle involving
reprocessing at Sellafield, a point that some
Irish observers find upsetting. However, this
probably uses less energy overall because,
although reprocessing requires extra energy,
25% less enrichment will be required. It is also
important to recognise that precise energy figures
for plant construction are not readily available,
although several studies use a factor converting
monetary inputs to energy.
Recent studies have compared different means
of generating electricity in energy and greenhouse
terms. Here are some of their results,
together with earlier data. The energy ratio is
simply output divided by input for the full life
cycle. Unlike some others in use, the R3 energy
ratio employs a convention which converts
between electrical and thermal energy, including
a thermal efficiency factor, so is used here.
Nevertheless the reciprocal percentage, the
input as a percentage of a plant's lifetime output,
may be more meaningful.
(Figure 1D3) Life Cycle Energy Ratios for Various Technologies |
| | R3 Energy
Ratio.
(output/input) |
Input % of
lifetime
output |
Hydro | Uchiyama 1996 | 50 | 2.0 |
| Held et al 1977 | 43 | 2.3 |
Quebec | Gagnon et al 2002 | 205 | 0.5 |
Nuclear (centrifuge enrichment) | see Table 1D2. | 59 | 1.7 |
PWR/BWR | Kivisto 2000 | 59 | 1.7 |
PWR | Inst. Policy Science 1977* | 46 | 2.2 |
BWR | Inst. Policy Science 1977* | 43 | 2.3 |
BWR | Uchiyama et al 1991* | 47 | 2.1 |
Nuclear (diffusion enrichment) | see Table 1d. | 21 | 4.8 |
PWR/ BWR | Held et al 1977 | 20 | 5.0 |
PWR/BWR | Kivisto 2000 | 17 | 5.8 |
| Uchiyama 1996 | 24 | 4.2 |
PWR | Oak Ridge Assoc.Univ. 1976* | 15.4 | 6.5 |
BWR | Oak Ridge Assoc.Univ. 1976* | 16.4 | 6.1 |
BWR | Uchiyama et al 1991* | 10.5 | 9.5 |
Coal | Kivisto 2000 | 29 | 3.5 |
| Uchiyama 1996 | 17 | 5.9 |
| Uchiyama et al 1991* | 16.8 | 6.0 |
| Inst. Policy Science 1977* | 14.2 | 7.0 |
unscrubbed | Gagnon et al 2002 | 7 | 14 |
Natural gas- piped | Kivisto 2000 | 26 | 3.8 |
piped 2000 km | Gagnon et al 2002 | 5 | 20 |
LNG | Uchiyama et al 1991* | 5.6 | 17.9 |
LNG (57% capacity factor) | Uchiyama 1996 | 6 | 16.7 |
Solar | Held et al 1997 | 10.6 | 9.4 |
Solar PV rooftop | Uchiyama 1996 | 9 | 11.1 |
utility | Uchiyama 1996 | 5 | 20.0 |
amorphous silicon | Kivisto 2000 | 3.7 | 27 |
Wind | Resource Research Inst. 1983* | 12 | 8.3 |
| Uchiyama 1996 | 6 | 16.7 |
| Kivisto 2000 | 34 | 2.9 |
| Gagnon et al 2002 | 80 | 1.3 |
Biomass forestry waste | Gagnon et al 2002 | 27 | 3.7 |
plantation | Gagnon et al 2002 | 5 | 20 |
* In IAEA 1994, TecDoc 753.
These figures show that energy ratios are clearly
sensitive not only to the amount of energy
used to build the power source and supply it
with whatever it needs to run, but also to the
proportion of the time at which it is delivering
power - in other words, its capacity factor.
This is particularly true where a significant
amount of energy is required to build the power
plant. The higher the energy input to build the
plant, the more output is needed to amortise it.
With technologies such as wind, where a turbine
will only be producing whenever the wind
blows, and then at a rate dependent on the wind
speed, a longer period is required to cover the
inputs due to lower capacity factors. Energy
payback period for the construction of a nuclear
power plant is 3-4 months, which compares
favourably with all except gas combined cycle.
The Liquid Natural Gas (LNG) figures quoted
are for natural gas compressed cryogenically
and shipped to Japan and used largely for peak
loads. The solar and wind figures relate to
intermittent inputs of primary energy, with
inevitably low capacity utilisation and relatively
high energy costs in the plant (for silicon
manufacture in the case of solar cells, or steel
and concrete for wind turbines).
The Swedish utility Vattenfall has undertaken a
thorough life cycle assessment of its Forsmark
nuclear power station, which has three boiling
water reactors totalling 3100 MWe net. These
started up in 1980-84 and run at 86.4% capacity.
The energy analysis figures (input as % of
output, transport included, 40 yr plant life, with
PJ figures calculated from % on basis of 3272
PJ output) are shown in figure 1D4 below.
(Figure 1D4) Energy analysis of a Swedish nuclear power station |
| input as % of output | PJ (calculated) |
Mine | 0.44 | 14 |
Refining & conversion | 3.18 | 104 |
Enrichment (80:20 centrifuge:diffusion) | 3.00 | 98 |
Fuel fabrication | 1.34 | 44 |
Plant operation | 0.28 | 9.2 |
Plant build & decommission | 0.27 | 8.8 |
Waste management | 0.11 | 3.6 |
Waste build & decommission | 0.01 | |
Total life cycle: | 8.70% | 285 PJ |
The Vattenfall Life Cycle Analysis study tracks
energy inputs further back than others, and so is
only comparable with data based on similar
methodology. Even so, some major variances
are unexplained - notably refining and conversion.
Uchiyama (1996) points out that hydro, nuclear
and fossil fuel plants have high energy ratios of
output over inputs because of their higher energy
density as well as capacity factors. Wind and
solar, however, are under 10 because of their
lower energy density, or output in relation to
plant volume and hence materials used.
LIFE CYCLE ANALYSIS: GREENHOUSE GASES
A principal concern of life cycle analysis for
energy systems today is their likely contribution
to global warming. This is a major external
cost.
If all energy inputs are assumed to be from
coal-fired plants that release about one tonne of
carbon dioxide per MWh, it is possible to
derive a greenhouse contribution from the energy
ratio. With major inputs, this is worth investigating
further.
Uranium enrichment in USA is by diffusion and
some of this capacity is supplied by coal-fired
plants. If a national average, allowing for different
sources of power, is applied, this input
has a value of around 650 kg CO2/MWh. This
gives a greenhouse contribution for nuclear
power of about 40kg/MWh overall. In France,
however, which has the world's largest diffusion
enrichment plant, electricity is supplied by
on-site nuclear reactors (which also supply the
grid). Because of this, the greenhouse contribution
from any nuclear reactor using Frenchenriched
uranium is similar to a reactor using
centrifuge-enriched uranium -- less than 1kg
/MWh for the enrichment input, and less than
20 kg/MWh overall.
Rashad and Hammad conclude that the life
cycle CO2emission coefficient for nuclear
power, on the basis of centrifuge enrichment, is
2.7% of that for coal-fired generation. This is
consistent with other figures based on fossil
fuel inputs.
Adding further confirmation to figures already
published from Scandinavia, Japan's Central
Research Institute of the Electric Power
Industry has published life cycle carbon dioxide
emission figures for various generation technologies.
Vattenfall (1999) has published a popular
account of life cycle studies based on the
previous few years experience and its certified
Environmental Product Declarations (EPDs)
for Forsmark and Ringhals nuclear power stations
in Sweden, and Kivisto in 2000 reports a
similar exercise for Finland. They show the
CO2 emissions in the table below.
The Japanese gas figures include shipping LNG
from overseas, and the nuclear figure is for
boiling water reactors, with enrichment 70% in
USA, 30% France & Japan, and one third of the
fuel to be MOX. The Finnish nuclear figures
are for centrifuge and diffusion enrichment
respectively, the Swedish one is for 80%
centrifuge.
(Figure 1D5) Relative carbon dioxide emissions from different energy sources |
g/kWh CO2 | Japan | Sweden | Finland | |
coal | 975 | 980 | 894 |
gas thermal | 608 | 1170 (peak-load, reserve) | - |
gas combined cycle | 519 | 450 | 472 |
solar photovoltaic | 53 | 50 | 95 |
wind | 29 | 5.5 | 14 |
nuclear | 22 | 6 | 10 - 26 |
hydro | 11 | 3 | - |
OTHER EXTERNAL COSTS
The report of ExternE, a major European study
of the external costs of various fuel cycles,
focusing on coal and nuclear, was released in
2001. The European Commission launched the
project in 1991 in collaboration with the US
Dept of Energy (which subsequently dropped
out), and it was the first research project of its
kind "to put plausible financial figures against
damage resulting from different forms of electricity
production for the entire EU".
The external costs are defined as those actually
incurred in relation to health and the environment
and quantifiable but not built into the cost
of the electricity to the consumer and therefore
which are borne by society at large. They
include particularly the effects of air pollution
on human health, crop yields and buildings, as
well as occupational disease and accidents. In
ExternE they exclude effects on ecosystems and
the impact of global warming, which could not
adequately be quantified and evaluated economically.
The methodology measures emissions, their
dispersion and ultimate impact. With nuclear
energy the (low) risk of accidents is factored in
along with high estimates of radiological
impacts from mine tailings and carbon-14 emissions
from reprocessing (waste management
and decommissioning being already within the
cost to the consumer).
The report shows that in clear cash terms
nuclear energy incurs about one tenth of the
costs of coal. In particular, the external costs for
coal-fired power were a very high proportion
(50-70%) of the internal costs, while the external
costs for nuclear energy were a very small
proportion of internal costs, even after factoring
in hypothetical nuclear catastrophes. This is
because all waste costs in the nuclear fuel cycle
are internalised, which reduces the competitiveness
of nuclear power when only internal costs
are considered. The external costs of nuclear
energy averages 0.4 euro cents/kWh, much the
same as hydro, coal is over 4.0 cents (4.1 - 7.3
cent averages in different countries), gas ranges
1.3-2.3 cents and only wind shows up better
than nuclear, at 0.1-0.2 cents/kWh average.
The EU cost of electricity generation without
these external costs averages about 4
cents/kWh. If these external costs were in fact
included, the EU price of electricity from coal
would double and that from gas would increase
30%. These particular estimates are without
attempting to include possible impacts of fossil
fuels on global warming. See also web:
http://externe.jrc.es/
Another European treatment of production and
external costs, specifically of power generation
in Switzerland, has recently been done by the
Paul Scherrer Institut and shows that the damage
costs from fossil fuels range from 10%
(gas) to 350% (coal) of the production costs,
while those for nuclear are very small. A summary
is accessible on the web:
http://gabe.web.psi.ch/
An earlier European study (Krewitt et al, 1999)
quantified environmental damage costs from
fossil fuel electricity generation in the EU for
1990 as US$ 70 billion, about 1% of GDP. This
included impacts on human health, building
materials and crop production, but not global
warming.
The ExternE report proposes two ways of
incorporating external costs: taxing the costs or
subsidising alternatives. Due to the difficulty of
taxing in an EU context, the subsidy route is
favoured. EC guidelines published in February
2001 encourage member states to subsidise
"new plants producing renewable energy ... on
the basis of external costs avoided", up to 5
c/kWh. However, this provision does not
extend to nuclear power, despite the comparable
external costs avoided. EU member countries
have pledged to have renewables (including
hydro) provide 12% of total energy and
22% of electricity by 2010, a target that appears
unlikely to be met. The case for extending the
subsidy to nuclear energy is obvious, particularly
if climate change is to be taken seriously.
Consideration of external costs leads to the conclusion
that the public health benefits associated
with reducing greenhouse gas emissions
from fossil fuel burning could be the strongest
reason for pursuing them. Considering four
cities - New York, Mexico, Santiago and Sao
Paulo - with total 45 million people, a 2001
paper in Science presents calculations showing
that some 64,000 deaths would be avoided in
the two decades to 2020 by reducing fossil fuel
combustion in line with greenhouse abatement
targets. This is consistent with a 1995 WHO
estimate of 460,000 avoidable deaths annually
from suspended particulates, largely due to outdoor
urban exposure.
The World Health Organisation in 1997 presented
two estimates, of 2.7 or 3 million deaths
occurring each year as a result of air pollution.
In the latter estimate: 2.8 million deaths were
due to indoor exposures and 200,000 to outdoor
exposure. The lower estimate comprised 1.85
million deaths from rural indoor pollution,
363,000 from urban indoor pollution and
511,000 from urban ambient pollution. The
WHO report points out that these totals are
about 6% of all deaths, and the uncertainty of
the estimates means that the range should be
taken as 1.4 to 6 million deaths annually attributable
to air pollution.
OTHER CONCERNS ABOUT NUCLEAR
POWER
In discussions of the relative merits of different
means of producing electricity, several concerns
are commonly raised regarding nuclear
power. This is not the place to treat them comprehensively,
but I will attempt a paragraph on
each of four:
RESOURCES
Uranium is abundant. The world's present
measured resources of uranium in the IAEANEA
lower cost category (3.1 million tonnes)
and used only in conventional reactors, are
enough to last for almost 50 years. This represents
a higher level of assured resources than is
normal for most minerals. Further exploration
and higher prices will certainly, on the basis of
present geological knowledge, yield further
resources as present ones are used up. This is
indicated in the figures if those covering estimates
of all conventional resources are considered
15.4 million tonnes, which is 240 years'
supply at today's rate of consumption. This figure
still ignores unconventional resources such
as phosphate deposits (22 Mt) and seawater (up
to 4000 Mt). But before recourse to them, widespread
use of the fast breeder reactor could
increase the utilisation of uranium sixty-fold or
more. It is well-proven but currently uneconomic
due to low uranium prices. Using uranium
for electricity is responsible in relation to
allowing for the needs of future generations.
WASTES
Virtually all wastes from the civil nuclear fuel
cycle are contained and managed. Certainly
none cause any harm to people or the environment,
nor pose any significant credible threat,
with the possible exception of reprocessing
where high-level wastes are in liquid form for a
time. High-level wastes mainly comprise, or are
derived from, spent fuel. They must be shielded
and cooled, neither of which is difficult or complex.
As spent fuel, they are in stable ceramic
form, and if reprocessed they end up thus.
Storage under water or in shielded concrete
structures is simple and safe. For final disposal
some 50 years ex reactor, they will be encapsulated
and placed in deep repositories, well
down towards where radiogenic decay of uranium
already heats the earth. The distinguishing
feature of radioactive wastes is that their toxicity
decays, unlike most other industrial wastes -
after 40 years from reactor, the radioactivity of
spent fuel has decayed to one thousandth of its
original level, and it is producing less than one
kilowatt of heat per tonne. Apart from renewables,
nuclear power is the only energy-producing
industry which takes full responsibility for
all its wastes, and fully costs this into the product.
SAFETY
From the outset, the safety of nuclear reactors
(where one has a very high energy density) has
been a high priority in their design and engineering.
About one third of the cost of a typical
reactor is due to safety systems and structures.
The Chernobyl accident in 1986 was a reminder
of the need for this (normal safety provisions
being largely absent there), whereas the comparable
Three Mile Island accident in 1979
showed that such safety measures work - noone
was harmed. In fact, and despite
Chernobyl, the safety record of nuclear power
is better than for any other major industrial
technology. And it is improving with newer
reactors.
WEAPONS PROLIFERATION
An early concern as nuclear technology
emerged from its military chrysalis was that
civil nuclear power should not enable more
countries to acquire nuclear weapons. Under
the Nuclear Non-Proliferation Treaty a safeguards
system was set up to detect and deter
any diversion of fissile material from civil to
military use. It is arguably the UN's most successful
program, and early prospects of 20-30
countries with nuclear weapons have been
averted. Today, the flow of material is from
weapons stockpiles to civil use, filling about
one fifth of world uranium demand. One in ten
light globes in the USA are now lit by ex-
Russian military uranium.
The WNA web site www.world-nuclear.org has
information papers on all these issues and many
more.
This is one of almost 50
chapters and articles in the 336-page large format book, Before the Wells
Run Dry. Copies of the book are available for £9.95 from Green Books. |
|
Continue to Section A of Part Two: A Sustainable Future - the Limits to Renewables
Sitemap for Before the Wells Run Dry